Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-05-07 |
Kickoff | 2024-05-15 |
Stage 3 - 60% | 2024-11-23 |
Stage 4 - 95% | 2025-02-13 |
EPG Clearance | 2024-12-21 |
RW Clearance | 2024-12-21 |
URR Clearance | 2025-02-13 |
Stage 5 - 100% | 2025-03-13 |
Advertise | 2025-04-04 |
Bids Opening | 2025-05-02 |
Award Date | 2025-05-31 |
|
Arizona Department of Transportation |