Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2021-10-27 A
Kickoff 2021-11-17 A
Stage 2 - 30% 2022-03-18 A
Stage 3 - 60% 2021-10-29 A
Stage 4 - 95% 2022-01-28 A
EPG Clearance 2022-01-20 A
RW Clearance 2022-01-21 A
URR Clearance 2022-03-28 A
Stage 5 - 100% 2022-04-15 A
Advertise 2022-09-07 A