RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 CH HCY T050301C SC SKYLINE DR; SR90 - LANDFILL ENTRA LD1Q ROADWAY RECONSTRUCTION JUDAH CAIN
602-712-4493
5/29/2025 Lee Makler
602-712-8579
Current Program Budget $1,566,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-04-26 A
Kickoff 2024-06-12 A
Stage 2 - 30% 2024-10-04 A
Stage 3 - 60% 2024-10-22 A
Stage 4 - 95% 2025-02-11
EPG Clearance 2025-02-11
RW Clearance 2025-04-11
URR Clearance 2025-02-11
Stage 5 - 100% 2025-05-03
Advertise 2025-05-29
Bids Opening 2025-07-19