Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2020-10-09 A
Kickoff 2020-10-12 A
Stage 1 - 15% 2021-01-11 A
Stage 2 - 30% 2020-12-09 A
Stage 3 - 60% 2021-06-30 A
Stage 4 - 95% 2022-04-22 A
EPG Clearance 2021-11-22 A
RW Clearance 2022-07-22 A
URR Clearance 2022-04-19 A
Stage 5 - 100% 2022-08-26 A
Advertise 2022-09-13 A
Bids Opening 2023-01-23 A
Award Date 2023-01-23 A