Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2019-01-31 A |
Kickoff | 2019-01-31 A |
Stage 2 - 30% | 2020-03-13 A |
Stage 3 - 60% | 2022-07-07 A |
Stage 4 - 95% | 2023-08-28 A |
EPG Clearance | 2020-07-07 A |
RW Clearance | 2023-09-18 A |
URR Clearance | 2023-10-11 A |
Stage 5 - 100% | 2023-11-03 A |
Advertise | 2023-12-21 A |
Bids Opening | 2024-03-15 A |
|