Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2020-09-09 A |
Kickoff | 2021-07-28 A |
Stage 2 - 30% | 2021-07-28 A |
Stage 3 - 60% | 2021-10-27 A |
Stage 4 - 95% | 2023-04-03 A |
EPG Clearance | 2021-08-23 A |
RW Clearance | 2023-10-19 A |
URR Clearance | 2021-11-30 A |
Stage 5 - 100% | 2024-04-03 |
Advertise | 2024-05-18 |
Bids Opening | 2024-06-22 |
|