Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2025-02-04 |
Kickoff | 2025-03-22 |
Stage 1 - 15% | 2026-01-28 |
Stage 2 - 30% | 2027-12-29 |
Stage 3 - 60% | 2028-04-19 |
Stage 4 - 95% | 2028-07-19 |
EPG Clearance | 2028-06-14 |
RW Clearance | 2028-08-30 |
Stage 5 - 100% | 2028-10-18 |
Advertise | 2029-02-21 |
|