RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 CN 248.0 F071501D NC TUCKER FLAT BRIDGE EB IS1Q REHABILITATE BRIDGE ARASH GHAZANFARI
602-712-8336
TBD Lee Makler
602-712-8579
Current Program Budget $4,000,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-05-16
Kickoff 2024-05-30
Stage 2 - 30% 2024-10-22
Stage 3 - 60% 2025-03-29
Stage 4 - 95% 2025-09-05
EPG Clearance 2025-07-01
RW Clearance 2025-10-31
URR Clearance 2025-10-17
Stage 5 - 100% 2026-02-11
Advertise 2026-07-16
Bids Opening 2026-07-31