ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 CN 248.0 F071501C NC TUCKER FLAT BRIDGE EB #336 IS1Q REHABILITATE BRIDGE ARASH GHAZANFARI
602-712-8336
7/16/2026 Lee Makler
602-712-8579
Current Program Budget $4,000,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-05-28 A
Kickoff 2024-06-12 A
Stage 2 - 30% 2024-11-15 A
Stage 3 - 60% 2025-03-27
Stage 4 - 95% 2025-10-23
EPG Clearance 2025-07-24
RW Clearance 2025-12-18
URR Clearance 2025-12-04
Stage 5 - 100% 2025-12-25
Advertise 2026-07-16
Bids Opening 2026-07-31




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation