ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 PN CSG T047001C SC CITY OF CASA GRANDE; FLORENCE BLV II1Q INSTALL RAISED MEDIAN VIVIAN LI
602-712-8708
6/26/2025 Lee Makler
602-712-8579
Current Program Budget $413,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-06-26 A
Kickoff 2024-06-27 A
Stage 2 - 30% 2024-09-23 A
Stage 3 - 60% 2025-01-16
EPG Clearance 2025-03-01
RW Clearance 2025-03-27
URR Clearance 2025-04-03
Stage 5 - 100% 2025-04-11
Advertise 2025-06-27
Bids Opening 2025-07-27




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation