Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
264 NA 380.0 F067801C NE SR 264 / IR 4, PHASE II ID1Q CONSTRUCT PEDESTRIAN PATH LINA BEARAT
602-712-8495
2/20/2026 Lee Makler
602-712-8579
Current Program Budget $755,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-09-07
Kickoff 2024-09-25
Stage 2 - 30% 2025-05-24
Stage 3 - 60% 2025-08-23
Stage 4 - 95% 2025-10-25
EPG Clearance 2025-10-11
RW Clearance 2025-12-06
URR Clearance 2025-12-13
Stage 5 - 100% 2026-01-24
Advertise 2026-02-21
Bids Opening 2026-04-18