RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
999 SW 0.0 F067901D NE VARIOUS LOCATIONS - STATEWIDE RWI HU1Q UPGRADE RWIS CHRIS RODRIGUEZ
602-617-9560
9/17/2024 Lee Makler
602-712-8579
Current Program Budget $350,000 Program FY 23

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-12-15 A
Kickoff 2024-01-11 A
Stage 2 - 30% 2024-01-26 A
Stage 3 - 60% 2024-06-04
Stage 4 - 95% 2024-07-30
EPG Clearance 2024-07-30
RW Clearance 2024-07-20
URR Clearance 2024-08-15
Stage 5 - 100% 2024-09-04
Advertise 2024-09-17
Bids Opening 2024-11-22