Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-04-04 A |
Kickoff | 2024-05-09 A |
Stage 2 - 30% | 2024-09-23 A |
Stage 3 - 60% | 2025-04-05 |
Stage 4 - 95% | 2025-08-05 |
EPG Clearance | 2025-05-31 |
RW Clearance | 2025-08-12 |
URR Clearance | 2025-08-13 |
Stage 5 - 100% | 2025-09-02 |
Advertise | 2025-11-08 |
Bids Opening | 2026-01-24 |
|
Arizona Department of Transportation |