| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2023-08-31 A |
| Kickoff | 2023-10-26 A |
| Stage 2 - 30% | 2024-04-23 A |
| Stage 3 - 60% | 2024-12-19 A |
| Stage 4 - 95% | 2025-03-10 A |
| EPG Clearance | 2025-02-25 A |
| RW Clearance | 2025-01-13 A |
| URR Clearance | 2025-04-25 A |
| Stage 5 - 100% | 2025-05-02 A |
| Advertise | 2025-05-29 A |
| Bids Opening | 2026-01-17 |
| |