| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2024-02-26 A |
| Kickoff | 2024-03-11 A |
| Stage 2 - 30% | 2024-07-26 A |
| Stage 3 - 60% | 2024-10-28 A |
| Stage 4 - 95% | 2025-02-13 A |
| EPG Clearance | 2024-12-24 A |
| RW Clearance | 2025-04-02 A |
| URR Clearance | 2025-03-25 A |
| Stage 5 - 100% | 2025-06-05 A |
| Advertise | 2025-06-16 A |
| Bids Opening | 2025-10-03 A |
| |