RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
347 PM 175.7 F067301C CL W JUAN ST - I-10 GW1Q PAVEMENT REHABILITATION LINA BEARAT
602-712-8495
TBD Lee Makler
602-712-8579
Current Program Budget $27,800,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-11-20 A
Kickoff 2023-11-20 A
Stage 2 - 30% 2023-11-20 A
Stage 3 - 60% 2024-03-03 A
Stage 4 - 95% 2025-05-01
EPG Clearance 2025-04-17
RW Clearance 2025-05-15
URR Clearance 2025-05-29
Stage 5 - 100% 2025-06-12
Advertise 2025-07-08
Bids Opening 2025-07-09