ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
160 CN 321.0 F064401C NC TUBA CITY - MP 335 GM1Q PAVEMENT REHABILITATION PATRICK O'LESKE
602-712-7629
8/13/2025 Lee Makler
602-712-8579
Current Program Budget $28,651,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-11-08 A
Kickoff 2023-11-13 A
Stage 2 - 30% 2023-11-13 A
Stage 3 - 60% 2024-12-07
Stage 4 - 95% 2025-03-22
EPG Clearance 2025-03-22
RW Clearance 2025-04-26
URR Clearance 2025-04-01
Stage 5 - 100% 2025-04-26
Advertise 2025-08-13
Bids Opening 2025-09-19




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation