Current Program Budget $17,720,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-11-08 A
Kickoff 2023-11-13 A
Stage 2 - 30% 2023-11-13 A
Stage 3 - 60% 2024-06-01
Stage 4 - 95% 2024-07-27
EPG Clearance 2024-07-27
RW Clearance 2024-08-03
URR Clearance 2024-08-06
Stage 5 - 100% 2024-08-17
Advertise 2024-10-09
Bids Opening 2024-11-22