Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-08-15 A |
Stage 2 - 30% | 2023-10-02 A |
Stage 3 - 60% | 2024-05-01 |
Stage 4 - 95% | 2025-07-12 |
EPG Clearance | 2024-06-29 |
RW Clearance | 2025-03-22 |
URR Clearance | 2025-03-29 |
Stage 5 - 100% | 2025-05-07 |
Advertise | 2025-07-19 |
Bids Opening | 2025-09-20 |
|
Arizona Department of Transportation |