RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
70 GH 335.0 F064701C SE REAY LN - 8TH ST GI1Q PAVEMENT REHABILITATION REHNUMA RAHMAN
602-712-7342
8/15/2025 Lee Makler
602-712-8579
Current Program Budget $17,288,000 Program FY 26

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-08-02 A
Stage 3 - 60% 2024-04-05 A
Stage 4 - 95% 2024-12-07
EPG Clearance 2024-12-07
RW Clearance 2024-12-14
URR Clearance 2025-02-01
Stage 5 - 100% 2025-04-26
Advertise 2025-05-31
Bids Opening 2025-07-19