ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
187 PN 186.8 F064101C SC SR 387 - SR 87 GH1Q PAVEMENT REHABILITATION TRICIA BROWN
602-712-7046
5/23/2025 Lee Makler
602-712-8579
Current Program Budget $15,084,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-07-31 A
Kickoff 2023-08-16 A
Stage 2 - 30% 2023-09-14 A
Stage 3 - 60% 2023-12-08 A
Stage 4 - 95% 2024-09-30 A
EPG Clearance 2025-04-01 A
RW Clearance 2024-12-20 A
URR Clearance 2025-04-01 A
Stage 5 - 100% 2025-01-27 A
Advertise 2025-05-24
Bids Opening 2025-08-16




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation