Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 MA GLN T011901C CL PHASE III-CITY OF GLENDALE FLASHI GD1O CONVERSION TO FLASHING YELLOW ARROWS ANGELA GALIETTI
602-712-7551
3/29/2024 Phil Schaffer
602 712-6845
Current Program Budget $2,750,000 Program FY 22

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2017-08-04 A
Kickoff 2017-08-14 A
Stage 2 - 30% 2017-10-12 A
Stage 3 - 60% 2018-02-22 A
Stage 4 - 95% 2022-01-13 A
EPG Clearance 2018-11-28 A
RW Clearance 2021-12-08 A
URR Clearance 2022-02-24 A
Stage 5 - 100% 2022-05-18 A
Advertise 2022-06-28 A
Bids Opening 2022-08-05 A
Award Date 2024-07-06




For Project Resource Office information or questions: PRO Mailbox