Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2017-08-04 A |
Kickoff | 2017-08-14 A |
Stage 2 - 30% | 2017-10-12 A |
Stage 3 - 60% | 2018-02-22 A |
Stage 4 - 95% | 2022-01-13 A |
EPG Clearance | 2018-11-28 A |
RW Clearance | 2021-12-08 A |
URR Clearance | 2022-02-24 A |
Stage 5 - 100% | 2022-05-18 A |
Advertise | 2024-11-05 A |
Bids Opening | 2022-08-05 A |
Award Date | 2024-12-21 |
|
Arizona Department of Transportation |