RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 MO 71.7 F063701D NW US 93 - SILVER SPRING RD GA1Q PAVEMENT REHABILITATION OLIVIER MIRZA
602-712-4032
7/10/2026 Lee Makler
602-712-8579
Current Program Budget $16,831,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-08-04 A
Stage 3 - 60% 2024-03-11 A
Stage 4 - 95% 2024-08-03
EPG Clearance 2024-06-08
RW Clearance 2024-08-10
URR Clearance 2024-08-13
Stage 5 - 100% 2024-08-13
Advertise 2026-07-11
Bids Opening 2026-09-19