ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 MO 71.7 F063701C NW US 93 - SILVER SPRING RD GA1Q PAVEMENT REHABILITATION OLIVIER MIRZA
602-712-4032
7/10/2026 Lee Makler
602-712-8579
Current Program Budget $16,831,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-08-04 A
Stage 3 - 60% 2024-03-11 A
Stage 4 - 95% 2024-10-05
EPG Clearance 2024-06-17 A
RW Clearance 2025-01-11
URR Clearance 2025-01-16
Stage 5 - 100% 2025-01-16
Advertise 2025-08-02
Bids Opening 2025-10-18




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation