Active Project List |
Return to Project listing | Print this page | |||||||||||||||||||||||||||||||||
|
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2024-06-06 |
Kickoff | 2024-06-29 |
Stage 1 - 15% | 2024-11-23 |
Stage 2 - 30% | 2024-10-01 |
Stage 3 - 60% | 2025-03-01 |
Stage 4 - 95% | 2025-10-24 |
EPG Clearance | 2026-01-24 |
RW Clearance | 2025-04-26 |
Stage 5 - 100% | 2026-01-23 |
Advertise | 2026-05-29 |
|
Arizona Department of Transportation |