Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-09-11 A |
Stage 3 - 60% | 2024-01-31 A |
Stage 4 - 95% | 2024-04-08 A |
EPG Clearance | 2024-03-07 A |
RW Clearance | 2024-03-22 A |
URR Clearance | 2024-04-26 A |
Stage 5 - 100% | 2024-08-16 |
Advertise | 2024-09-13 |
Bids Opening | 2024-10-19 |
|