Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-10-17 A |
Kickoff | 2023-11-15 A |
Stage 2 - 30% | 2024-05-02 A |
Stage 3 - 60% | 2024-10-11 A |
Stage 4 - 95% | 2024-12-06 |
EPG Clearance | 2024-12-07 |
RW Clearance | 2024-12-21 |
URR Clearance | 2024-12-21 |
Stage 5 - 100% | 2025-02-15 |
Advertise | 2025-02-15 |
Bids Opening | 2025-04-19 |
|