ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
19 PM 61.0 F048801C SC IRVINGTON RD TI EQ1G CONSTRUCT TI SIVA SIVAKUMAR
602-371-4570
2/18/2025 Lee Makler
602-712-8579
Current Program Budget $32,012,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-04-04 A
Kickoff 2023-04-19 A
Stage 2 - 30% 2024-02-28 A
Stage 3 - 60% 2024-06-25
Stage 4 - 95% 2024-09-27
EPG Clearance 2024-08-15
RW Clearance 2024-10-04
URR Clearance 2024-09-24
Stage 5 - 100% 2024-11-26
Advertise 2025-02-18




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation