Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Kickoff | 2023-05-18 A |
Stage 1 - 15% | 2023-10-02 A |
Stage 2 - 30% | 2023-08-30 A |
Stage 3 - 60% | 2023-09-29 A |
Stage 4 - 95% | 2024-03-01 A |
EPG Clearance | 2024-03-04 A |
RW Clearance | 2024-03-01 A |
Advertise | 2024-06-01 |
|