RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 MO 56.5 H681401C NW RANCHO SANTA FE PARKWAY TI EC1H CONSTRUCT NEW TI ANGELA GALIETTI
602-712-7551
6/14/2024 Lee Makler
602-712-8579
Current Program Budget $0 Program FY 24
Cost Estimate Amount
Design Stage II $36,055,027.12
Design Stage III $35,614,112.73
Design Stage IV $37,871,417.93
Scoping Estimate $35,968,791.00

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2020-08-17 A
Kickoff 2019-09-23 A
Stage 4 - 95% 2020-09-24 A
URR Clearance 2021-11-01 A
Stage 5 - 100% 2024-05-31
Advertise 2024-06-14
Bids Opening 2024-08-16