Active Project List |
Return to Project listing | Print this page |
Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
Kickoff | 2019-07-10 A |
Stage 1 - 15% | 2020-01-06 A |
Stage 2 - 30% | 2020-03-06 A |
Stage 3 - 60% | 2021-02-26 A |
Stage 4 - 95% | 2022-03-11 A |
EPG Clearance | 2020-09-10 A |
RW Clearance | 2022-03-23 A |
URR Clearance | 2022-04-11 A |
Stage 5 - 100% | 2022-08-15 A |
Advertise | 2022-09-06 A |
Bids Opening | 2022-11-18 A |
Award Date | 2023-01-20 A |
|