Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-09-01 A |
Kickoff | 2023-11-29 A |
Stage 2 - 30% | 2024-04-16 A |
Stage 3 - 60% | 2024-12-25 |
Stage 4 - 95% | 2025-08-09 |
EPG Clearance | 2025-08-06 |
RW Clearance | 2026-04-18 |
URR Clearance | 2026-05-23 |
Stage 5 - 100% | 2025-11-08 |
Advertise | 2027-04-03 |
Bids Opening | 2027-05-15 |
|