Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-09-01 A |
Kickoff | 2023-10-17 A |
Stage 2 - 30% | 2024-02-23 A |
Stage 3 - 60% | 2024-06-19 |
Stage 4 - 95% | 2024-09-06 |
EPG Clearance | 2024-08-07 |
RW Clearance | 2024-09-20 |
URR Clearance | 2024-10-02 |
Stage 5 - 100% | 2024-11-08 |
Advertise | 2024-12-13 |
Bids Opening | 2025-01-24 |
|