RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
93 MO 106.0 F060101C NW CANE SPRINGS DO1M CONSTRUCT 4-LANE DIVIDED HIGHWAY BHARAT KANDEL
602-712-8736
6/25/2024 Lee Makler
602-712-8579
Current Program Budget $110,300,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-07-21 A
Kickoff 2023-08-08 A
Stage 2 - 30% 2023-10-27 A
Stage 3 - 60% 2024-02-05 A
Stage 4 - 95% 2024-03-29 A
EPG Clearance 2024-05-07 A
RW Clearance 2024-06-12 A
URR Clearance 2024-05-22 A
Stage 5 - 100% 2024-05-24 A
Advertise 2024-06-25 A
Bids Opening 2024-07-20