RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
0000 YU YUM T040901C SW CITY OF YUMA; 3 CITYWIDE LOCATION DI1Q FLASHING YELLOW ARROW SIGNALS CHRIS MOORE
602-712-2132
TBD Lee Makler
602-712-8579
Current Program Budget $331,000 Program FY 27

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-06-21 A
Stage 3 - 60% 2023-11-30 A
Stage 4 - 95% 2025-11-13
EPG Clearance 2024-02-26 A
RW Clearance 2025-12-03
URR Clearance 2025-12-16
Stage 5 - 100% 2025-12-16
Advertise 2026-01-14
Bids Opening 2025-02-08