RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 AP 331.0 F059401C NE SANDERS & TOPOCK POE DG1Q TIRE ANOMALY SENSORS CHRIS MOORE
602-712-2132
2/27/2025 Lee Makler
602-712-8579
Current Program Budget $260,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-03-01 A
Kickoff 2023-03-08 A
Stage 3 - 60% 2023-04-26 A
Stage 4 - 95% 2024-12-13
EPG Clearance 2023-07-25 A
RW Clearance 2023-09-22 A
URR Clearance 2023-08-04 A
Stage 5 - 100% 2025-02-06
Advertise 2025-02-27
Award Date 2025-03-22