Project Milestones
Milestone Name Date  ("A" denotes actual finish)
Kickoff 2024-11-13 A
Stage 2 - 30% 2025-04-08 A
Stage 3 - 60% 2025-08-29 A
Stage 4 - 95% 2025-10-22
EPG Clearance 2025-10-02
RW Clearance 2025-10-22
URR Clearance 2025-10-30
Stage 5 - 100% 2026-01-29
Advertise 2026-03-17
Bids Opening 2026-05-29