RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
40 CN 186.0 F028101C NC TRANSWESTERN RD - I-17 TI CC1P VARIABLE SPEED LIMIT SIGNS & SUPPORTING ITS INFRAS WESLEY SCATENA
602-712-8555
5/31/2024 Jeff Ross
602-712-8477
Current Program Budget $4,200,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2020-05-22 A
Kickoff 2020-05-22 A
Stage 2 - 30% 2020-05-22 A
Stage 3 - 60% 2020-09-09 A
Stage 4 - 95% 2023-08-10 A
EPG Clearance 2023-08-10 A
RW Clearance 2021-01-11 A
URR Clearance 2021-01-11 A
Stage 5 - 100% 2024-05-03
Advertise 2024-06-01




For Project Resource Office information or questions: PRO Mailbox