Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-07-05 A
Kickoff 2023-06-09 A
Stage 2 - 30% 2023-07-31 A
Stage 3 - 60% 2023-08-21 A
Stage 4 - 95% 2024-01-30 A
EPG Clearance 2024-01-30 A
RW Clearance 2024-02-21 A
URR Clearance 2024-03-05 A
Stage 5 - 100% 2024-03-25 A
Advertise 2024-05-01
Bids Opening 2024-06-05