Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
89 CN 548.3 F055801C NC N LAKE POWELL BLVD BJ1Q INSTALL ROUNDABOUT SANDY THOMS
602-712-7607
6/12/2024 Lee Makler
602-712-8579
Current Program Budget $715,000 Program FY 23

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-03-27 A
Kickoff 2023-04-20 A
Stage 3 - 60% 2023-12-05 A
Stage 4 - 95% 2024-03-14 A
EPG Clearance 2024-02-15 A
RW Clearance 2024-05-30
URR Clearance 2024-05-23
Stage 5 - 100% 2024-05-24
Advertise 2024-06-13
Bids Opening 2024-08-15