RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
303L MA 136.1 F056201C CL 51ST AVE - I-17 BI1Q GENERAL PURPOSE LANE & TI RAMPS SANDY THOMS
602-712-7607
6/20/2025 Lee Makler
602-712-8579
Current Program Budget $235,980,000 Program FY 25

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-06-07 A
Kickoff 2023-07-12 A
Stage 2 - 30% 2023-09-15 A
Stage 3 - 60% 2024-03-04 A
Stage 4 - 95% 2024-06-24 A
EPG Clearance 2025-04-14 A
RW Clearance 2024-07-23 A
URR Clearance 2025-04-26
Stage 5 - 100% 2025-05-17
Advertise 2025-06-21
Bids Opening 2025-08-02