ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
303L MA 136.7 F056201C CL 51ST AVE - I-17 BI1Q GENERAL PURPOSE LANE & TI RAMPS SANDY THOMS
602-712-7607
7/18/2025 Lee Makler
602-712-8579
Current Program Budget $19,000,000 Program FY 23

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-06-07 A
Kickoff 2023-07-12 A
Stage 2 - 30% 2023-09-15 A
Stage 3 - 60% 2024-03-04 A
Stage 4 - 95% 2024-06-24 A
EPG Clearance 2025-02-15
RW Clearance 2024-07-23 A
URR Clearance 2024-12-14
Stage 5 - 100% 2025-06-17
Advertise 2025-07-18
Bids Opening 2025-08-29




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation