Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-05-04 A |
Kickoff | 2023-06-08 A |
Stage 2 - 30% | 2023-08-25 A |
Stage 3 - 60% | 2024-02-08 A |
Stage 4 - 95% | 2024-06-01 |
EPG Clearance | 2024-05-25 |
RW Clearance | 2024-06-22 |
URR Clearance | 2024-06-29 |
Stage 5 - 100% | 2024-09-14 |
Advertise | 2024-10-17 |
Bids Opening | 2024-11-28 |
|