Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-04-25 A |
Kickoff | 2023-05-31 A |
Stage 2 - 30% | 2023-11-17 A |
Stage 3 - 60% | 2024-03-28 A |
Stage 4 - 95% | 2024-10-16 A |
EPG Clearance | 2024-11-25 A |
RW Clearance | 2024-10-18 A |
URR Clearance | 2024-11-28 |
Stage 5 - 100% | 2025-01-18 |
Advertise | 2025-02-15 |
Bids Opening | 2025-04-19 |
|