Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
95 LA 109.1 F059101C SW TYSON ST - N. OF QUARTZSITE AF1Q PAVEMENT REHABILITATION PEDRAM SHAFIEIAN
602-712-8166
6/28/2024 Lee Makler
602-712-8579
Current Program Budget $12,514,000 Program FY 24

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2023-04-12 A
Stage 3 - 60% 2024-02-22 A
Stage 4 - 95% 2024-04-30
EPG Clearance 2024-05-25
RW Clearance 2024-04-12 A
URR Clearance 2024-06-07
Stage 5 - 100% 2024-06-04
Advertise 2024-06-29
Bids Opening 2024-08-27