Project Milestones | |
---|---|
Milestone Name | Date ("A" denotes actual finish) |
NTP | 2023-04-12 A |
Stage 3 - 60% | 2024-02-22 A |
Stage 4 - 95% | 2024-05-06 A |
EPG Clearance | 2024-05-29 A |
RW Clearance | 2024-04-12 A |
URR Clearance | 2024-05-17 A |
Stage 5 - 100% | 2024-06-04 |
Advertise | 2024-06-25 A |
Bids Opening | 2024-08-27 |
|