ADOTNet : Home

Active Project List



Return to Project listing | Print this page

 
RT CO MP TRACS D PROJECT NAME CPSID TYPE OF WORK PROJECT MANAGER BID ADV SCHEDULER
93 YV 190.5 F073801C NW VISTA ROYALE AE1Q CONSTRUCT TO 4 LANES DIVIDED TRICIA BROWN
602-712-7046
5/31/2028 Lee Makler
602-712-8579
Current Program Budget $46,500,000 Program FY 28

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2028-06-02
Kickoff 2028-06-02
Stage 2 - 30% 2028-06-02
Stage 3 - 60% 2028-06-02
Stage 4 - 95% 2028-06-02
EPG Clearance 2028-06-02
RW Clearance 2028-06-02
URR Clearance 2028-06-02
Stage 5 - 100% 2028-06-02
Advertise 2028-06-02
Bids Opening 2028-06-02




For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation