| Project Milestones | |
|---|---|
| Milestone Name | Date ("A" denotes actual finish) |
| NTP | 2024-10-31 A |
| Kickoff | 2024-12-02 A |
| Stage 2 - 30% | 2025-05-12 A |
| Stage 3 - 60% | 2025-10-01 A |
| Stage 4 - 95% | 2025-12-17 |
| EPG Clearance | 2025-11-01 |
| RW Clearance | 2026-02-25 |
| URR Clearance | 2026-01-01 |
| Stage 5 - 100% | 2026-02-19 |
| Advertise | 2026-07-01 |
| Bids Opening | 2026-08-01 |
| Award Date | 2026-09-19 |
| |