93 YV 190.5 F073801C NW VISTA ROYALE AE1Q CONSTRUCT TO 4 LANES DIVIDED TRICIA BROWN
602-712-7046
5/31/2028 Lee Makler
602-712-8579
Current Program Budget $46,500,000 Program FY 28

Project Milestones
Milestone Name Date  ("A" denotes actual finish)
NTP 2024-10-31 A
Kickoff 2024-12-02 A
Stage 2 - 30% 2025-04-08
Stage 3 - 60% 2025-08-27
Stage 4 - 95% 2025-12-17
EPG Clearance 2025-08-27
RW Clearance 2026-02-25
URR Clearance 2026-01-01
Stage 5 - 100% 2026-02-19
Advertise 2026-07-01
Bids Opening 2026-08-01
Award Date 2026-09-19