SEP 12 OCT 12 NOV 12 DEC 12 JAN 13 FEB 13 MAR 13 APR 13 MAY 13 JUN 13 JUL 13 AUG 13 SEP 13 OCT 13 NOV 13 DEC 13 JAN 14 FEB 14 MAR 14 APR 14 MAY 14 JUN 14 JUL 14 AUG 14 SEP 14 OCT 14 NOV 14 DEC 14 JAN 15 FEB 15 MAR 15 APR 15 MAY 15 JUN 15 JUL 15 AUG 15 SEP 15 OCT 15 NOV 15 DEC 15 JAN 16 FEB 16 MAR 16 APR 16 MAY 16 JUN 16 JUL 16 AUG 16 SEP 16 OCT 16 NOV 16 DEC 16 JAN 17 FEB 17 MAR 17 APR 17 MAY 17 JUN 17 JUL 17 AUG 17 SEP 17 OCT 17 NOV 17 DEC 17 JAN 18 FEB 18 MAR 18 APR 18 MAY 18 JUN 18 JUL 18 AUG 18 SEP 18 OCT 18 NOV 18 DEC 18 JAN 19 FEB 19
R239XFA PE Federal Authorization (Obtained) 09/20/2012 09/20/2012 09/20/2012 09/20/2012
  u 100%
  u  
R242XPL Design Stage II Submittal 09/20/2012 01/21/2014 09/20/2012 01/21/2014
    100%
     
R21AXPL IGA Complete 10/15/2012 10/15/2012 10/15/2012 10/15/2012
  u 100%
  u  
R240XPL1 Kick Off Meeting 12/06/2012 12/06/2012 12/06/2012 12/06/2012
  u 100%
  u  
R243XPL Design Stage III Submittal 01/22/2014 03/03/2015 01/22/2014 03/03/2015
    100%
     
R24404PS Initial Matierial Memo 02/27/2015 02/27/2015 02/27/2015 02/27/2015
  u 100%
  u  
R24606EP NEPA Approval 08/13/2015 08/13/2015 08/13/2015 08/13/2015
  u 100%
  u  
R246XEP Environmental Clearance 08/13/2015 08/13/2015 08/13/2015 08/13/2015
  u 100%
  u  
R243XPL10 Design Stage III Comment Resolution 03/04/2016 03/15/2016 03/04/2016 03/15/2016
    100%
     
R244XPL Design Stage IV Submittal 03/07/2016 01/07/2019 03/07/2016 01/07/2019
     
     
R2CS998 Bid Advertisement Package Ready 09/26/2016 09/26/2016 09/26/2016 09/26/2016
  u  
  u  
R246XRW Right of Way Clearance 09/26/2016 12/21/2016 09/26/2016 12/21/2016
     
     
R246XUR Utilities & Railroad Clearance 09/26/2016 12/21/2016 09/26/2016 12/21/2016
     
     
R243XPS Final Material Memo 09/26/2016 10/17/2016 09/26/2016 10/17/2016
     
     
R245XPL Submit Final PS&E 01/08/2019 01/10/2019 01/08/2019 01/10/2019
     
     
R2CS960 C&S Finalize Bid Package & Clearances 01/11/2019 02/08/2019 01/11/2019 02/08/2019
     
     