OP1L PRO Gantt Chart
ADOTNet : Home

Active Project List



Cutoff Date: 10/15/2018
0% = Task not started | 100% = Task completed

Activity Activity
Name
Planned
Start
Planned
Finish
Early/Actual
Start
Early/Actual
Finish
MAY 14 JUN 14 JUL 14 AUG 14 SEP 14 OCT 14 NOV 14 DEC 14 JAN 15 FEB 15 MAR 15 APR 15 MAY 15 JUN 15 JUL 15 AUG 15 SEP 15 OCT 15 NOV 15 DEC 15 JAN 16 FEB 16 MAR 16 APR 16 MAY 16 JUN 16 JUL 16 AUG 16 SEP 16 OCT 16 NOV 16 DEC 16 JAN 17 FEB 17 MAR 17
N442DCR10 Initial DCR Due 05/30/2014 05/30/2014 05/30/2014 05/30/2014
  u 100%
  u  
N440XEPN NEPA Approval (Obtained) 07/13/2015 07/13/2015 07/13/2015 07/13/2015
  u 100%
  u  
N446XEP Environmental (NEPA) Clearance 07/13/2015 07/13/2015 07/13/2015 07/13/2015
  u 100%
  u  
N442DCR20 Final DCR Due 09/26/2016 11/10/2016 09/26/2016 11/10/2016
     
     
N443XPL Design Stage III Submittal 09/26/2016 11/22/2016 09/26/2016 11/22/2016
     
     
N42AXPL Pre-Design/Scoping (Complete) 09/26/2016 09/26/2016 09/26/2016 09/26/2016
  u  
  u  
N4CS960 C&S Finalize Bid Package & Clearances 09/26/2016 10/24/2016 09/26/2016 10/24/2016
     
     
N443XPS Final Material Memo 11/23/2016 01/20/2017 11/23/2016 01/20/2017
     
     
N446XRW Right-of-Way Clearance 11/23/2016 01/20/2017 11/23/2016 01/20/2017
     
     
N446XUR Utility and Railroad Clearance 11/23/2016 01/20/2017 11/23/2016 01/20/2017
     
     
N445XPL Submit Final PS&E 01/23/2017 03/22/2017 01/23/2017 03/22/2017
     
     


For Project Resource Office information or questions: PRO Mailbox