MZ1H PRO Gantt Chart
ADOTNet : Home

Active Project List



Cutoff Date: 10/15/2018
0% = Task not started | 100% = Task completed

Activity Activity
Name
Planned
Start
Planned
Finish
Early/Actual
Start
Early/Actual
Finish
AUG 13 SEP 13 OCT 13 NOV 13 DEC 13 JAN 14 FEB 14 MAR 14 APR 14 MAY 14 JUN 14 JUL 14 AUG 14 SEP 14 OCT 14 NOV 14 DEC 14 JAN 15 FEB 15 MAR 15 APR 15 MAY 15 JUN 15 JUL 15 AUG 15 SEP 15 OCT 15 NOV 15 DEC 15 JAN 16 FEB 16 MAR 16 APR 16 MAY 16 JUN 16 JUL 16 AUG 16 SEP 16 OCT 16 NOV 16 DEC 16 JAN 17 FEB 17 MAR 17 APR 17 MAY 17 JUN 17 JUL 17 AUG 17 SEP 17
NK2AXPL10 Initial DCR Due 08/05/2013 05/19/2017 08/05/2013 05/19/2017
     
     
NK4406EP Draft Environmental Assessment (EA) 08/05/2013 05/31/2017 08/05/2013 05/31/2017
     
     
NK40XEPN NEPA Approval 11/30/2016 11/30/2016 11/30/2016 11/30/2016
  u  
  u  
NK2AXPL FINAL DCR Due 05/22/2017 07/07/2017 05/22/2017 07/07/2017
     
     
NK42XPL Design Stage II Submottal 07/10/2017 08/18/2017 07/10/2017 08/18/2017
     
     
NK43XPS Final Materials Memo 08/21/2017 08/25/2017 08/21/2017 08/25/2017
     
     
NK46XEP Environmental Clearance 08/21/2017 08/25/2017 08/21/2017 08/25/2017
     
     
NK46XRW Right of Way Clearance 08/21/2017 08/25/2017 08/21/2017 08/25/2017
     
     
NK46XUR Utility and Railroad Clearance 08/21/2017 08/25/2017 08/21/2017 08/25/2017
     
     
NKCS960 C&S Finalize Bid Package & Clearances 08/28/2017 09/25/2017 08/28/2017 09/25/2017
     
     


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation