JUN 12 JUL 12 AUG 12 SEP 12 OCT 12 NOV 12 DEC 12 JAN 13 FEB 13 MAR 13 APR 13 MAY 13 JUN 13 JUL 13 AUG 13 SEP 13 OCT 13 NOV 13 DEC 13 JAN 14 FEB 14 MAR 14 APR 14 MAY 14 JUN 14 JUL 14 AUG 14 SEP 14 OCT 14 NOV 14 DEC 14 JAN 15 FEB 15 MAR 15 APR 15 MAY 15 JUN 15 JUL 15 AUG 15 SEP 15 OCT 15 NOV 15 DEC 15 JAN 16 FEB 16 MAR 16 APR 16 MAY 16 JUN 16 JUL 16 AUG 16 SEP 16 OCT 16 NOV 16 DEC 16 JAN 17 FEB 17 MAR 17 APR 17 MAY 17 JUN 17 JUL 17 AUG 17 SEP 17 OCT 17 NOV 17 DEC 17 JAN 18 FEB 18 MAR 18
ZP39XFA PE Federal Authorization (Obtained) 06/22/2012 06/22/2012 06/22/2012 06/22/2012
  u 100%
  u  
ZP40XPL Design Start 06/27/2014 06/27/2014 06/27/2014 06/27/2014
  u 100%
  u  
ZP40XPL1 Project Start-up/Kick-off 08/07/2014 08/07/2014 08/07/2014 08/07/2014
  u 100%
  u  
ZP46XEP Environmental Clearance 03/02/2015 10/16/2017 03/02/2015 10/16/2017
     
     
ZP42XPL Design Stage II Submittal 08/15/2016 10/28/2016 08/15/2016 10/28/2016
     
     
ZP1040 Design Stage II Comment & Resolution Meeting 10/31/2016 12/21/2016 10/31/2016 12/21/2016
     
     
ZP43XPL Design Stage III Submittal 12/22/2016 05/26/2017 12/22/2016 05/26/2017
     
     
ZP4303PL Design Stage III Comment & Resolution Meeting 05/30/2017 07/19/2017 05/30/2017 07/19/2017
     
     
ZP44XPL Design Stage IV Submittal 07/20/2017 09/28/2017 07/20/2017 09/28/2017
     
     
ZP4404PL Design Stage IV Comment & Resolution Meeting 09/29/2017 11/21/2017 09/29/2017 11/21/2017
     
     
ZP40XEPN NEPA Approval (Obtained) 10/16/2017 10/16/2017 10/16/2017 10/16/2017
  u  
  u  
ZP43XPS Material Memo 11/22/2017 11/29/2017 11/22/2017 11/29/2017
     
     
ZP46XRW Right-of-Way Clearance 11/22/2017 11/29/2017 11/22/2017 11/29/2017
     
     
ZP46XUR Utility and Railroad Clearance 11/22/2017 11/29/2017 11/22/2017 11/29/2017
     
     
ZP45XPL Submit Final PS&E 11/30/2017 12/07/2017 11/30/2017 12/07/2017
     
     
ZPCS998 Bid Advertisement Package Ready 12/01/2017 12/01/2017 12/01/2017 12/01/2017
  u  
  u  
ZPCS999 Bid Advertisement Date 03/05/2018 03/05/2018 03/05/2018 03/05/2018
  u  
  u  


For Project Resource Office information or questions: PRO Mailbox