LP1M PRO Gantt Chart
ADOTNet : Home

Active Project List



Cutoff Date: 10/15/2018
0% = Task not started | 100% = Task completed

Activity Activity
Name
Planned
Start
Planned
Finish
Early/Actual
Start
Early/Actual
Finish
NOV 13 DEC 13 JAN 14 FEB 14 MAR 14 APR 14 MAY 14 JUN 14 JUL 14 AUG 14 SEP 14 OCT 14 NOV 14 DEC 14 JAN 15 FEB 15 MAR 15 APR 15 MAY 15 JUN 15 JUL 15 AUG 15 SEP 15 OCT 15 NOV 15 DEC 15 JAN 16 FEB 16 MAR 16 APR 16 MAY 16 JUN 16 JUL 16 AUG 16 SEP 16 OCT 16 NOV 16 DEC 16 JAN 17 FEB 17 MAR 17 APR 17 MAY 17 JUN 17 JUL 17 AUG 17
3N41XPL Design Stage I (Complete) 07/02/2018 07/02/2018 11/01/2013 02/13/2015
 
   
3N42XPL Design Stage II (Complete) 02/28/2019 02/28/2019 09/26/2016 09/30/2016
 
     
3N46XEP Environmental Clearance (Obtained) 04/30/2019 04/30/2019 09/26/2016 11/29/2016
 
     
3N46XRW Right-of-Way Clearance (Obtained) 03/27/2020 03/27/2020 09/26/2016 08/04/2017
 
     
3N43XPL Design Stage III (Complete) 05/24/2019 05/24/2019 10/03/2016 10/25/2016
 
     
3NCS998 Bid Advertisement Package Ready 05/25/2050 05/25/2050 10/14/2016 10/14/2016
 
  u  
3N44XPL Design Stage IV (Complete) 12/20/2019 12/20/2019 10/26/2016 02/14/2017
 
     
3N46XUR Utility and Railroad Clearance (Obtained) 03/27/2020 03/27/2020 11/09/2016 11/16/2016
 
     
3N43XPS Final MAterials Memo 12/13/2019 12/13/2019 11/09/2016 11/16/2016
 
     
3N45XPL Final PS&E (Complete) 04/03/2020 04/03/2020 02/15/2017 03/14/2017
 
     