JJ1N PRO Gantt Chart
ADOTNet : Home

Active Project List



Cutoff Date: 10/15/2018
0% = Task not started | 100% = Task completed

Activity Activity
Name
Planned
Start
Planned
Finish
Early/Actual
Start
Early/Actual
Finish
NOV 14 DEC 14 JAN 15 FEB 15 MAR 15 APR 15 MAY 15 JUN 15 JUL 15 AUG 15 SEP 15 OCT 15 NOV 15 DEC 15 JAN 16 FEB 16 MAR 16 APR 16 MAY 16 JUN 16 JUL 16 AUG 16 SEP 16 OCT 16 NOV 16 DEC 16 JAN 17 FEB 17
5B2AXPL Pre-Design/Scoping (Complete) 11/17/2014 11/17/2014 11/17/2014 11/17/2014
  u 100%
  u  
5B43XPL Design Stage III (Complete) 08/04/2015 08/04/2015 08/04/2015 08/04/2015
  u 100%
  u  
5B44XPL Design Stage IV (Complete) 03/18/2016 03/18/2016 03/18/2016 03/18/2016
  u 100%
  u  
5B46XEP Environmental Clearance (Obtained) 11/01/2016 11/01/2016 11/01/2016 11/01/2016
  u  
  u  
5B46XUR Utility and Railroad Clearance (Obtained) 12/09/2016 12/09/2016 12/09/2016 12/09/2016
  u  
  u  
5B45XPL Final PS&E (Complete) 12/16/2016 12/16/2016 12/16/2016 12/16/2016
  u  
  u  
5B46XRW Right-of-Way Clearance (Obtained) 12/20/2016 12/20/2016 12/20/2016 12/20/2016
  u  
  u  
5BCS998 Bid Advertisement Package Ready 12/30/2016 12/30/2016 12/30/2016 12/30/2016
  u  
  u  
5BCS999 Bid Advertisement Date 02/28/2017 02/28/2017 02/28/2017 02/28/2017
  u
  u


For Project Resource Office information or questions: PRO Mailbox