EY1N PRO Gantt Chart
ADOTNet : Home

Active Project List



Cutoff Date: 10/15/2018
0% = Task not started | 100% = Task completed

Activity Activity
Name
Planned
Start
Planned
Finish
Early/Actual
Start
Early/Actual
Finish
JUL 14 AUG 14 SEP 14 OCT 14 NOV 14 DEC 14 JAN 15 FEB 15 MAR 15 APR 15 MAY 15 JUN 15 JUL 15 AUG 15 SEP 15 OCT 15 NOV 15 DEC 15 JAN 16 FEB 16 MAR 16 APR 16 MAY 16 JUN 16 JUL 16 AUG 16 SEP 16 OCT 16 NOV 16 DEC 16 JAN 17
XW39XFA PE Federal Authorization (Obtained) 07/02/2018 07/02/2018 07/10/2014 07/10/2014
 
  u  
XW41XPL Design Stage I Submittal 07/02/2018 07/02/2018 02/24/2015 06/01/2015
 
     
XW42XPL Design Stage II Submittal 09/26/2016 10/17/2016 09/26/2016 10/17/2016
     
     
XW40XPL1 Project Start-up/Kick-off 07/02/2018 07/02/2018 09/26/2016 09/26/2016
 
  u  
XWCS998 Bid Advertisement Package Ready 08/16/2019 08/16/2019 09/26/2016 09/26/2016
 
  u  
XW46XEP Environmental Clearance 07/02/2018 07/02/2018 09/26/2016 12/06/2016
 
     
XW43XPL Design Stage III Submittal 07/02/2018 07/02/2018 10/18/2016 10/31/2016
 
     
XW43XPS Material Memo 07/02/2018 07/02/2018 11/01/2016 12/05/2016
 
     
XW44XPL Design Stage IV Submittal 07/02/2018 07/02/2018 11/01/2016 11/22/2016
 
     
XW46XRW Right-of-Way Clearance 07/02/2018 07/02/2018 11/01/2016 12/05/2016
 
     
XW46XUR Utility and Railroad Clearance 07/02/2018 07/02/2018 11/01/2016 12/05/2016
 
     
XW45XPL Submit Final PS&E 07/15/2019 07/15/2019 12/07/2016 12/20/2016
 
     
XWCS960 C&S Finalize Bid Package & Clearances 12/21/2016 01/20/2017 12/21/2016 01/20/2017
     
     