EN1M PRO Gantt Chart
ADOTNet : Home

Active Project List



Cutoff Date: 10/15/2018
0% = Task not started | 100% = Task completed

Activity Activity
Name
Planned
Start
Planned
Finish
Early/Actual
Start
Early/Actual
Finish
JUL 13 AUG 13 SEP 13 OCT 13 NOV 13 DEC 13 JAN 14 FEB 14 MAR 14 APR 14 MAY 14 JUN 14 JUL 14 AUG 14 SEP 14 OCT 14 NOV 14 DEC 14 JAN 15 FEB 15 MAR 15 APR 15 MAY 15 JUN 15 JUL 15 AUG 15 SEP 15 OCT 15 NOV 15 DEC 15 JAN 16 FEB 16 MAR 16 APR 16 MAY 16 JUN 16 JUL 16 AUG 16 SEP 16 OCT 16 NOV 16 DEC 16 JAN 17 FEB 17 MAR 17 APR 17
IP39XFA PE Federal Authorization (Obtained) 07/05/2013 07/05/2013 07/05/2013 07/05/2013
  u 100%
  u  
IP46XEP Environmental Clearance 07/01/2015 04/06/2017 07/01/2015 04/06/2017
     
     
IP2AXPL1 Pre-Initial DCR 07/14/2016 07/14/2016 07/14/2016 07/14/2016
  u 100%
  u  
IP40XEPN NEPA Approval (Obtained) 09/26/2016 09/26/2016 09/26/2016 09/26/2016
  u  
  u  
IP2AXPL2 Initial DCR 10/17/2016 10/17/2016 10/17/2016 10/17/2016
  u  
  u  
IP2AXPL3 Pre-Final DCR 12/15/2016 12/15/2016 12/15/2016 12/15/2016
  u  
  u  
IP2AXPL Pre-Design/Scoping (Complete) (Final DCR) 02/15/2017 02/15/2017 02/15/2017 02/15/2017
  u  
  u  